Compressed delivery programme

The project was awarded in February 2024, completed and dispatched in August, entered trial production in October and achieved final acceptance in December.

Process organization for high-end grades

The line integrates furnace equipment, atmosphere circulation, temperature control, automation and production-data management, with a planned annual throughput of 70,000 tonnes. Metallurgical, decarburization and energy-performance values are governed by the technical agreement and project acceptance results.

Bell-furnace equipment at the project site
Bell-furnace equipment at the project site
Automation and production-monitoring interface
Automation and production-monitoring interface